Kassier Bypass Rd Phase 1A Opened - February 2023

Kassier Bypass Rd Opened

On 14th February 2023, the Kassier Bypass Rd opened with motorists travelling between the N3 and P559/Milky Way (both north and south) doing so on a newly built tar road.…
Kassier Rd - Phase 1A bypass under construction - December 2022

Kassier Rd – Phase 1A Bypass

The 2023 construction period has begun and the Westown development team is back on site, with a focus on the Kassier Rd – Phase 1A bypass and clearing the site…
Westown Aerial Flyover

Westown Aerial Flyover

In a Westown Aerial Flyover video captured at the end of November 2022, the development of Westown site can clearly be seen. The construction of the bypass along Kassier Rd…

Kassier Road Upgrade In The Media

The upgrade of Kassier Rd is long overdue and the commitment by the City to the funding of this work has enabled Westown to begin development.  Because of the extent…
Westown is using dynamic compaction

Westown Is Using Dynamic Compaction

Westown is using dynamic compaction, a construction technique that will compact the soil on site in preparation for the bulk earthworks for Westown Square. Not a common practice in KwaZulu-Natal,…
Kassier Rd upgrade plans

The Kassier Road Upgrade Plans

The upgrade of Kassier Rd is long overdue and the commitment by the City to the funding of this work has enabled Westown to begin development. This upgrade, along with…

Who Is Developing Westown?

Who Is Developing Westown? The development of Westown is led by Durban-based Fundamentum Property Group through the Fundamentum Development Company (FDC) which owns the development rights to Westown.

Main contractor Stefanutti Stocks

Main Contractor Stefanutti Stocks

Construction of Westown Shongweni begins at the end of August with the upgrade of Kassier Rd, a project that will be headed up by the main contractor Stefanutti Stocks.