First Goal Of March 2025

Posted on 4 March 2024
First Goal Of March 2025

Over the last 12 months, the Westown Square and Kassier Rd construction teams have been steadily working towards the first goal of March 2025 when Kassier Rd’s upgrade will be complete and Westown Square will be open for business.

This work has resulted in some pretty impressive numbers being racked up, including:

????‍13 400m³ of concrete poured
????2 200 tons of rebar used
????12 800m² of roof sheeting placed
????5 000m² of bricks laid
????1.3km of piling driven
????8.4km of roadbed laid
????3.4km of deviation road created
????780m of stormwater pipes laid
????5.5km of cable ducts installed
????‍61 trainees through the Academy
????68 pieces of heavy machinery on site

It’s all systems go as we move into the last 12 months of construction with the first goal of March 2025 signifying the completion of the first projects within the greater Westown development.

Read more about the greater Westown development

Previous Post
Westown Square Has Picked Up The Pace
Next Post
Road Upgrade Momentum Increasing

Recent Posts

  • Best New Retail Development
  • Bok Fan Park
  • Westown Trail Test Run
  • Update On Kassier Road
  • Boks Vs All Blacks

Categories

  • All Posts
  • Behind The Scenes
  • Events
  • JTL @ Westown
  • Landscape & Greening
  • Media and News
  • One Year On
  • Outer West
  • Road Upgrades
  • Shongweni Eco Park
  • Tenant Mix
  • The Barn
  • This Is Westown
  • Uncategorised
  • Westown Construction
  • Westown Foundation
  • Westown Launch
  • Westown Square
Quick Links

Home
About Westown
Westown Square & The Barn
Shongweni Eco-Park
Westown Precincts
Virtual Tour
News
Gallery

Contact & Social

Contact Us

Facebook
YouTube
LinkedIn
Instagram
TikTok

© Westown